Pre-Fabricated Implementation Applied to Clariant Integration Park (Occ)
16 September 2020    Pageviews:764

As one of the world's leading specialty chemicals companies headquartered in Switzerland, Clariant is actively supporting the transformation of Chinese chemical industry with innovative and sustainable solutions, increased capacity and enhanced local cooperation. Strategy setting and coordination has been greatly improved through the establishment of a new regional governance model in which top Chinese managers are responsible for profits and losses.

The Clariant Integrated Park (OCC) in Shanghai, scheduled for completion in 2020, includes an integrated regional headquarters and innovation facilities that continue to deliver ultra-high value to customers in a wide range of industries.

The new modular laboratory project of Clariant Integrated Park in Shanghai undertaken by Dynaflow.The laboratory project is 1-4 floors with a construction area of about 4800 square meters.With an estimated completion date of Oct 31st, clariant will be provided with an environmentally safe, upscale, elegant and sustainable laboratory.

In clariant project, Dynaflow adopts assembly technology to carry out the overall implementation, using modular combination technology of IS system, through BIM design, modular production, mechanized construction, precise management and other means, to improve the on-site implementation efficiency and progress.Assembly technology covers the whole life cycle of the laboratory, with intensive, environmental protection, energy saving, sustainable and other characteristics, is conducive to greatly improve the use effect and service life of the laboratory.

Prefabricated laboratories reduce construction time by 97%, manual by 99%, aerial work by 98% and on-site pollutant emissions by 90%.Prefabricated construction is the main form of green building, the maximum use of social resources and the minimum impact of social environment, is to build a new building model of ecological development.

Pre-Fabricated Implementation Applied to Clariant Integration Park (Occ)
16 September 2020    Pageviews:764

As one of the world's leading specialty chemicals companies headquartered in Switzerland, Clariant is actively supporting the transformation of Chinese chemical industry with innovative and sustainable solutions, increased capacity and enhanced local cooperation. Strategy setting and coordination has been greatly improved through the establishment of a new regional governance model in which top Chinese managers are responsible for profits and losses.

The Clariant Integrated Park (OCC) in Shanghai, scheduled for completion in 2020, includes an integrated regional headquarters and innovation facilities that continue to deliver ultra-high value to customers in a wide range of industries.

The new modular laboratory project of Clariant Integrated Park in Shanghai undertaken by Dynaflow.The laboratory project is 1-4 floors with a construction area of about 4800 square meters.With an estimated completion date of Oct 31st, clariant will be provided with an environmentally safe, upscale, elegant and sustainable laboratory.

In clariant project, Dynaflow adopts assembly technology to carry out the overall implementation, using modular combination technology of IS system, through BIM design, modular production, mechanized construction, precise management and other means, to improve the on-site implementation efficiency and progress.Assembly technology covers the whole life cycle of the laboratory, with intensive, environmental protection, energy saving, sustainable and other characteristics, is conducive to greatly improve the use effect and service life of the laboratory.

Prefabricated laboratories reduce construction time by 97%, manual by 99%, aerial work by 98% and on-site pollutant emissions by 90%.Prefabricated construction is the main form of green building, the maximum use of social resources and the minimum impact of social environment, is to build a new building model of ecological development.

CONTACT DYNAFLOW
Address: 10F, Building 1, District 3, Hanwei International Plaza, No. 186 South 4th Ring Road West, Fengtai District, Beijing
Landline: 010-52913779
Laboratory design, construction: 13264445390
Product sales: 13701003949
Purchase: 13810224876
Dynaflow Technology Co., Ltd | Original Part of the Website, Infringement Must Be Investigated Some of the Pictures on the Website. Copyright © Dynaflow All Rights Reserved. 京ICP备15054471号
ABOUT DYNAFLOW
Address: 10F, Building 1, District 3, Hanwei International Plaza, No. 186 South 4th Ring Road West, Fengtai District, Beijing
Landline: 010-52913779
Laboratory design, construction: 13264445390
Product sales: 13701003949
Purchase: 13810224876

Dynaflow Technology Co., Ltd | Original Part of the Website, Infringement Must Be Investigated Some of the Pictures on the Website.
Copyright © Dynaflow All Rights Reserved.
京ICP备15054471号